Blowup

Reviewed by licensed engineers

Checked against its sources by licensed professional engineers on the previous site, where reviewers weren’t recorded by name.

How articles are reviewed

On this page · 4 sections
  1. Description
  2. Problem
  3. Possible Causes
  4. Repair

Description

A localized upward slab movement and shattering at a joint or crack. Usually occurs in spring or summer and is the result of insufficient room for slab expansion during hot weather.

Blowup on SR 195 in eastern Washington.Blowup on SR 195 in eastern Washington.
Figures 1 and 2. Blowup on SR 195 in eastern Washington. Blowup on SR 195 in eastern Washington.

Problem

Roughness, moisture infiltration, safety hazard

Possible Causes

During cold periods (e.g., winter) PCC slabs contract leaving wider joint openings. If these openings become filled with incompressible material (such as rocks or soil), subsequent PCC slab expansion during hot periods (e.g., spring, summer) may cause high compressive stresses. This can be especially true when abnormally hot temperatures are encountered in a particular area. For instance, in the summer of 2021, the Seattle, Washington area experienced a record-breaking four-day (26-29 June) heat wave where each day was above 100F (Saturday through Monday) and culminating with an all-time high of 108F. Once this heat wave started, there were many accounts of concrete pavement blowups (or "buckling"). Ultimately, if high compressive stresses caused by adjacent slab expansion is great enough, the slabs may buckle and shatter at their joint to relieve the stresses. Blowup can be accelerated by:

  • Joint spalling (reduces slab contact area and provides incompressible material to fill the joint/crack)
  • D cracking (weakens the slab near the joint/crack area)
  • Freeze-thaw damage (weakens the slab near the joint/crack area)

Repair

Full-depth patch

Teaching this? Figures and worked examples are free to use with credit. Course reading lists

Cite this page

APA

Pavement Interactive. (2026, November 1). Blowup. HeadLight. Retrieved [the date you read it], from https://pavementinteractive.org/reference-desk/pavement-management/pavement-distresses/blowup/

ASCE

Pavement Interactive. (2026). “Blowup.” HeadLight, <https://pavementinteractive.org/reference-desk/pavement-management/pavement-distresses/blowup/> ([the date you read it]).

BibTeX

@misc{pavint-blowup,
  author = {{Pavement Interactive}},
  title = {Blowup},
  year = {2026},
  publisher = {HeadLight},
  howpublished = {\url{https://pavementinteractive.org/reference-desk/pavement-management/pavement-distresses/blowup/}},
  note = {Accessed [date]}
}
This address will not change. The citation records the date you read it.
Report an error

Reports go to the editors, who check them against the cited sources. Corrections are noted at the top of the article.

Only if you want a reply. It is not published.