PCC Placement
Reviewed by licensed engineers
Checked against its sources by licensed professional engineers on the previous site, where reviewers weren’t recorded by name.
PCC can be placed directly in the desired location by truck or truck attachments (see Figures 1 and 2), or can be fed into a placement machine for more accurate and even placement. PCC that is moved excessively once it has been unloaded from the transport truck will tend to segregate (become less homogeneous).


During the screeding (or strikeoff) process, excess portions of the roughly placed PCC are cut off in order to bring the slab to the required elevation. This is usually done by dragging a straightedge across the slab at the required elevation.
Teaching this? Figures and worked examples are free to use with credit. Course reading lists
Cite this page
APA
Pavement Interactive. (2018, September 5). PCC placement. HeadLight. Retrieved [the date you read it], from https://pavementinteractive.org/reference-desk/construction/placement/pcc-placement/
ASCE
Pavement Interactive. (2018). “PCC Placement.” HeadLight, <https://pavementinteractive.org/reference-desk/construction/placement/pcc-placement/> ([the date you read it]).
BibTeX
@misc{pavint-pcc-placement,
author = {{Pavement Interactive}},
title = {PCC Placement},
year = {2018},
publisher = {HeadLight},
howpublished = {\url{https://pavementinteractive.org/reference-desk/construction/placement/pcc-placement/}},
note = {Accessed [date]}
}